The World Bank has issued a fresh warning to the Kenyan government over delays in compensation payments that have stalled the construction of the KSh 168 billion Horn of Africa Gateway Development Project, raising concerns about rising costs and possible further delays.
The World Bank has issued a fresh warning to the Kenyan government over delays in compensation payments that have stalled the construction of the KSh 168 billion Horn of Africa Gateway Development Project, raising concerns about rising costs and possible further delays.
In a letter addressed to Treasury Cabinet Secretary John Mbadi, Roads and Transport Cabinet Secretary Davis Chirchir and Lands Cabinet Secretary Alice Wahome, the World Bank raised concerns over delays in compensating project-affected persons, warning that the situation was disrupting construction timelines and increasing the risk of additional costs.
According to the World Bank's Kenya Division Director, the delays in compensation were preventing contractors from accessing land freely, making it difficult for some sections of the road to proceed as planned.
The Bank indicated that although funds for compensation had already been released, payments to affected persons had not been completed, raising questions about transparency and the implementation of the compensation process.
The World Bank estimates that every additional month of delay exposes the project to approximately KSh 1.2 billion in extra costs. These include supervision, security, site facilities, idle equipment and personnel, price escalation and other time-related overheads. The amount also includes approximately KSh 207.5 million in equipment demobilization and remobilization costs.
"Based on the current estimates across the six active road contracts, each additional month of restricted site possession exposes the project to approximately KSh 1 billion in recurring costs," the letter stated.
"Despite the availability of credit proceeds for compensation since 2024, the compensation process did not begin until November 2025 and has so far been limited to the Isiolo–Modogashe road section. Delays would significantly increase the project's overall costs and implementation period."
The letter further revealed that only 1,281 project-affected persons had been compensated out of 1,669. The Kenyan government had paid approximately KSh 456 million in compensation for the Isiolo–Kulamawe section.
The World Bank warned that delays could expose the section to additional costs estimated at KSh 536 million per month.
Meanwhile, compensation for the Wajir–Tarbaj–Kotulo section was expected to be completed by November 2026 but has also faced delays, with additional costs estimated at KSh 421 million monthly.
The Kotulo–Kobo section has equally experienced delays in compensation claims, with an estimated monthly financial exposure of approximately KSh 243 million.
The 740-kilometre highway under the Horn of Africa Gateway Development Project was approximately 60 per cent complete as of October 2026. It was initially scheduled for completion in January 2028, but the completion timeline has since been pushed to around 2030.
The World Bank's warning raises concerns about the financial implications of prolonged compensation delays, which could further slow down construction and increase the overall cost of the project.